Due-window assignment scheduling with past-sequence-dependent setup times

Math Biosci Eng. 2022 Jan 19;19(3):3110-3126. doi: 10.3934/mbe.2022144.

Abstract

This article investigates the due-window assignment scheduling problem with setup times on a single machine, where setup times of jobs are past-sequence-dependent. Under common, slack and unrestricted due-window assignment methods, the goal is to determine the optimal job sequence and due-window such that the cost function (i.e., the weighted sum of earliness and tardiness, number of early and tardy jobs, due-window starting time and size) is minimized. We solve the problem optimally by introducing a polynomial time algorithm. An extension to the problem with learning and deterioration effects is also studied.

Keywords: due-window assignment; scheduling; setup times; single-machine.